On the Hardness of Scheduling With Non-Uniform Communication Delays
Sami Davies, Janardhan Kulkarni, Thomas Rothvoss, Sai Sandeep, Jakub Tarnawski, Yihao Zhang
摘要
In the scheduling with non-uniform communication delay problem, the input is a set of jobs with precedence constraints. Associated with every precedence constraint between a pair of jobs is a communication delay, the time duration the scheduler has to wait between the two jobs if they are scheduled on different machines. The objective is to assign the jobs to machines to minimize the makespan of the schedule. Despite being a fundamental problem in theory and a consequential problem in practice, the approximability of scheduling problems with communication delays is not very well understood. One of the top ten open problems in scheduling theory, in the influential list by Schuurman and Woeginger and its latest update by Bansal, asks if the problem admits a constant factor approximation algorithm. In this paper, we answer the question in negative by proving that there is a logarithmic hardness for the problem under the standard complexity theory assumption that NP-complete problems do not admit quasi-polynomial time algorithms.
Our hardness result is obtained using a surprisingly simple reduction from a problem that we call Unique Machine Precedence constraints Scheduling (UMPS). We believe that this problem is of central importance in understanding the hardness of many scheduling problems and conjecture that it is very hard to approximate. Among other things, our conjecture implies a logarithmic hardness of related machine scheduling with precedences, a long-standing open problem in scheduling theory and approximation algorithms.
问问这篇 Paper
智能体会读完全文。
Lune 把这篇 Paper 索引到了每一个公式,引用它的顶会 Paper 也一样。你提问,回答直接引用原文。
它引用的顶会 Paper6
- Efficient Algorithms for Device Placement of DNN Graph OperatorsJakub Tarnawski, Amar Phanishayee, Nikhil R. Devanur, Divya Mahajan 等NeurIPS 2020 · 被引用 84 次
- Scheduling with Communication Delays via LP Hierarchies and Clustering II: Weighted Completion Times on Related MachinesSami Davies, Janardhan Kulkarni, Thomas Rothvoss, Jakub Tarnawski 等SODA 2021 · 被引用 15 次
- Scheduling Precedence-Constrained Jobs on Related Machines with Communication DelayBiswaroop Maiti, Rajmohan Rajaraman, David Stalfa, Zoya Svitkina 等FOCS 2020 · 被引用 14 次
- Hierarchy-Based Algorithms for Minimizing Makespan under Precedence and Communication ConstraintsJanardhan Kulkarni, Shi Li, Jakub Tarnawski, Minwei YeSODA 2020 · 被引用 12 次
- Scheduling with Communication Delays via LP Hierarchies and ClusteringSami Davies, Janardhan Kulkarni, Thomas Rothvoss, Jakub Tarnawski 等FOCS 2020 · 被引用 10 次
相关 Paper
- A Subexponential Time Algorithm for Makespan Scheduling of Unit Jobs with Precedence ConstraintsJesper Nederlof, Céline M. F. Swennenhuis, Karol WegrzyckiSODA 2025
- Improved Approximation Algorithms for Non-preemptive Throughput MaximizationAlexander Armbruster, Fabrizio Grandoni, Antoine Tinguely, Andreas WieseSTOC 2026 · 被引用 1 次
- Towards PTAS for Precedence Constrained Scheduling via Combinatorial AlgorithmsShi LiSODA 2021 · 被引用 5 次
- An Approximation for Job Scheduling on Cloud with Synchronization and Slowdown ConstraintsDejun Kong, Zhongrui Zhang, Yangguang Shi, Xiaofeng GaoINFOCOM 2023 · 被引用 2 次
- Tight running times for minimum <italic>ℓq</italic>-norm load balancing: beyond exponential dependencies on 1/<italic>∊</italic>Lin Chen, Liangde Tao, José VerschaeSODA 2022 · 被引用 1 次